The first new mobile workover rigs to enter Venezuela’s oil fields in more than 15 years arrived this month. North American Blue Energy Partners (NABEP) announced on 13 October that eleven 550-horsepower units are being deployed across its operations, following two 1,500-horsepower drilling rigs that landed on 7 October. The company says it has bought 60 rigs, 30 steam boilers and 70 pieces of heavy machinery, and describes the result as the largest heavy-equipment fleet in the country. “Every rig that arrives in Venezuela brings us closer to reaching our production goals,” said Alejandro Betancourt, the company’s founder and chief executive.
Headline numbers are easy to announce. What matters is where each unit is and what it has added. NABEP’s own inventory answers that, field by field.
Why heavy oil needs hardware
Venezuela’s crude is among the heaviest in the world. In the Orinoco Belt it will not move without heat or diluent; on Lake Maracaibo, wells standing in open water need barges and wireline units to reach them, and old wells must be worked over repeatedly. Reservoirs do not disappear. What disappeared over a decade of underinvestment were the steam generators, service rigs and flowlines that kept them producing, and the pace at which that equipment returns sets the pace at which barrels do.
Steam: 22 units in the field, 66 planned
NABEP’s PetroZamora fields of Bachaquero and Lagunillas produce by cyclic steam injection, forcing steam into the reservoir to thin the oil. According to the company, 22 portable steam generation units are now operating: eight at Bachaquero, twelve at Lagunillas and two at Zuata 2 in the Belt. Five more are in transit and 44 are scheduled by 2027, for a fleet of 66, built to order by US manufacturers GBV Solutions and ACES.
Drilling: the first new wells in eight years
At Junin 10 in the Orinoco Belt, three drilling rigs are active and two more are being incorporated. One has intervened in ten wells and added about 3,950 barrels per day since February 2025; another has worked six wells and added about 2,680 since December 2025. In August, two new wells came on stream at around 450 barrels per day each, the first drilled in the field in eight years; two more followed in September.
Modest volumes against a 1 million barrel-per-day ambition, but that is how such an ambition is reached: one rig at a time, across a growing fleet. Internal documents seen by the Wall Street Journal set out a plan for six drilling rigs by the end of 2026, twelve more in 2027 and two a month from 2028 until the fleet reaches 52, with rigs sourced from Helmerich & Payne, Precision Drilling and Patterson-UTI.
Workover: the unglamorous majority
Most of the fleet is for keeping existing wells alive. At PetroZamora, NABEP lists twelve onshore service rigs, two repair-and-completion rigs, a drilling rig and, on the lake, two well-rehabilitation barges, a coiled-tubing unit and five wireline units. At Zuata 2 and Junin 10 there are six service and rod rigs. A workover rig moves from well to well, fixing what has failed; the 149 shut-in wells NABEP returned to production at Zuata 2 in early 2025 were recovered this way. The eleven units announced this month add to that base.
Heavy equipment and pipe
Behind the rigs sit 24 heavy units on land and 31 on the lake, 42 of them contracted rather than owned, which points to a service economy being rebuilt around the fields. Then there is pipe: flowlines have corroded or been stripped, and without them a reactivated well has nowhere to send its oil. NABEP has taken delivery of 514 kilometres of flexible pipe, with 5,222 kilometres more due by 2027, enough to run from Caracas to Buenos Aires.
Two sets of numbers
The 60 rigs, 30 boilers and 70 heavy units in the October announcement are procurement totals, including equipment in transit and on order; the inventory above is what is in the field today. Together they show a programme about a third of the way to its targets, with the balance arriving through 2027.
The test is output. Across the three assets NABEP operates directly, PetroZamora, Zuata 2 and Junin 10, production has roughly doubled from about 73,000 barrels per day at entry to about 152,000 in September, according to the company. Rystad Energy independently assesses that production across NABEP-associated operations has risen from roughly 90,000 barrels per day at the end of 2024 to nearly 200,000 today. NABEP’s own headline, first published when its agreement with the US government was announced on 31 August, is from approximately 18,000 to more than 200,000 in two years. The perimeters differ, but every figure was produced by the equipment described here.
An operator’s approach
Betancourt spent years in Venezuela’s oil sector before building NABEP, and the company is run as an operating business; the emphasis on steam, rigs and pipe reflects that. It is also the measure by which he and the company should be judged: not the fleet announced, but the barrels each unit adds and how quickly the next one follows. For a country whose output is at a seven-year high of about 1.2 million barrels per day, that is how the recovery will be built: with equipment, in the field, one well at a time.